2014-04-15 28 views
0

我们最近开始使用TFS 2012进行SCRUM方法,下面是我们当前的结构。我们有问题,与显示产品Backlog页面冲刺周期:TFS 2012 Scrum - 冲突周期在积压页面中显示不正确

>  Team Project 1 
>  |_Iteration 1 
>   |_ Sprint 1 of Iteration 1 (Start Date: 04/7/2014 End Date: 04/25/2014) 
>  |_Iteration 2 
>   |_ Sprint 1 of Iteration 2 (Start Date: 04/7/2014 End Date: 04/11/2014) 
>   |_ Sprint 2 of Iteration 2 (Start Date: 04/14/2014 End Date: 04/18/2014) 
>   |_ Sprint 3 of Iteration 2 (Start Date: 04/21/2014 End Date: 04/25/2014) 
>   |_ Sprint 4 of Iteration 2 (Start Date: 04/28/2014 End Date: 05/2/2014) 
>   
>   
>  When I look at the Product Backlog Page, this is what I see: 
>  Current 
>  |_ Sprint 1 of Iteration 1 (Start Date: 04/7/2014 End Date: 04/25/2014)  
>  Future 
>  |_ Sprint 1 of Iteration 2 (Start Date: 04/7/2014 End Date: 04/11/2014) 
>  |_ Sprint 2 of Iteration 2 (Start Date: 04/14/2014 End Date: 04/18/2014) 
>  |_ Sprint 3 of Iteration 2 (Start Date: 04/21/2014 End Date: 04/25/2014) 
>  |_ Sprint 4 of Iteration 2 (Start Date: 04/28/2014 End Date: 05/2/2014) 

在积压页面显示的配置是不正确的,因为“冲刺1 迭代2”是过去完成冲刺该图是未来,而“迭代2的冲刺2 ”是当前正在未来展现的冲刺。需要在TFS 2012中进行任何 配置更改吗?

回答

0

您的迭代日期有问题。迭代不是并行处理时间框。你应该认为他们是上冲刺。

所以在你的例子中,迭代1和2的sprint 1似乎是在同一天开始的,而这样的事情不可能发生。在完成迭代1之前,你不能跳转到迭代2.我认为你正在使用迭代作为项目分支,对吗?

+1

Enmos,谢谢你的回应。你是对的。我们正在使用迭代作为项目。我们有两个团队在一个项目中同时在一个项目中进行一个项目,一个项目在现场。我们希望分别跟踪每个团队的进度。两次迭代在每次迭代中都有多个sprint同时运行。有没有办法在TFS 2012中做到这一点? – Arun

+0

有一个团队模型可以帮助你。我个人不习惯它。 http://blog.nwcadence.com/working-within-a-single-team-project-with-team-foundation-server-2012/ – Montag451